OEE Solitaire is only applicable in situations where the monitored equipment has a technical link to other equipment/processes. Thus the equipment is an integrated part of a line. The effectiveness of such equipment is partially depending on factors like line balance and effectiveness of other equipment. ‘No Input’ (input buffer empty) and ‘No Output’ (Output buffer full) are the exponents of such influences. In certain case i.e. with huge installations in process industry parties may want to know the effectiveness of the equipment independently from the rest of the process. In other words; What would be the effectiveness of the equipment when it was running solitaire, with no restraints from the rest of the line?
For this purpose, an OEE can be calculated excluding ‘No Input’ and ‘No Output’ thus showing the effectiveness purely focussed on the equipment independent from the line. Calculating the OEE Solitaire takes Line restraint time (normally considered to be (I) Idle time) out of the loading time (so it is considered as Unscheduled time (-) ).
Caution: ‘No Input’/’No Output’ should not be confused with for example ‘no raw material’ or ‘no packaging’ since these have an other cause; they are not Line Restraints!
|